Project: QUORN FOODS NEW MIXER ROOM
locations: Stokesley
overall size of the project: Approx 50 sqm2
system: Polyurethane screed
- Prepare Substrate via means of vacuum-enclosed diamond grinding to provide a clean textured surface.
- Install New Stainless Steel Drainage.
- Install New Falls to room footprint.
- Once the room is installed apply a nominal 9mm polyurethane screed in chosen RAL colour.
- Apply polyurethane cove to all wall details.
- Apply polyurethane jointing materials to all edges, joints and drain details.
- The project was completed in 4 days.