Project: QUORN FOODS NEW MIXER ROOM

locations: Stokesley

overall size of the project: Approx 50 sqm2

system: Polyurethane screed

  • Prepare Substrate via means of vacuum-enclosed diamond grinding to provide a clean textured surface.
  • Install New Stainless Steel Drainage.
  • Install New Falls to room footprint.
  • Once the room is installed apply a nominal 9mm polyurethane screed in chosen RAL colour.
  • Apply polyurethane cove to all wall details.
  • Apply polyurethane jointing materials to all edges, joints and drain details.
  • The project was completed in 4 days.