Project: PROTEIN BASED FOOD MANUFACTURING PLANT

locations: Wroclaw – Poland

overall size of the project: Approx. 720M2

system: Flexible seamless polyurethane system to the mezzanine deck

  • Food processing plant.
  • Degreased and mechanically sand to prepare the substrate.
  • Cover all joints with fibreglass incorporated into the epoxy primer and allowed to cure.
  • Apply epoxy primer to all decks and allow to cure.
  • Apply 3-4mm seamless flexible polyurethane screed and allow to cure.
  • 1st matt seal
  • 2nd matt seal
  • Completed in 10 days.