Project: IPL SITTINGBOURNE
locations: Sittingbourne
overall size of the project: Approx 8,000 sqm2
specification: Polyurethane screed
- Prepare substrate via vacuum-enclosed shot-blasting to remove all surface contamination and leave a clean textured mechanical finish.
- Apply Moisture Tolerant Primer to the entire area and blind with quartz aggregates.
- Saw-cut anchor points to all perimeters of each individual concrete slab and the entire building area.
- Apply nominal 9mm polyurethane screed to all areas.
- Recut and bring through each concrete joint and apply polyurethane jointing compound.
- The project was completed in 25 days.