image
image
image
image

Project: IPL LTD NEW WASH ROOM

locations: Telford

overall size of the project: Approx 10sqm2

specification: Polyurethane screed

  • Remove all existing failed epoxy coating and prepare substrate via vacuum-enclosed diamond grinding.
  • Cut all perimeter anchor points and transitions.
  • Apply DPM primer and Polyurethane underlayment to create fall to drains.
  • Apply 9mm polyurethane screed in chosen Ral.
  • Apply polyurethane jointing compound to all joints and transitions
  • Project completed in 3 days.