Project: IPL LTD FORKTUCK TURNING SIDE
locations: Telford
overall size of the project: Approx 90sqm2
specification: Polyurethane screed
- Remove all existing failed epoxy coating and prepare substrate via vacuum-enclosed diamond grinding.
- Cut all perimeter anchor points and transitions.
- Prime all areas with Epoxy DPM primer and blind with quartz aggregates.
- Apply 6mm polyurethane screed in chosen Ral.
- The project was completed in 2 days.