Project: A FOOD MANUFACTURING PLANT

locations: Northamptonshire UK

overall size of the project: approx. 75 M2

system: polymer screed underlay. Polyurethane topping with expansion joints

  • Washroom.
  • Prepared by diamond grinders with vacuum attached.
  • Apply 1st epoxy dpm primer and broadcast with quartz.
  • Apply polymer fibrous screed to falls and allow to cure.
  • To perform diamond toe-in cuts and apply TF polyurethane primer and allow it to cure.
  • To lay a 9mm polyurethane screed.
  • To diamond cut all expansion joints and fill with 2 x part jointing compound.
  • To apply clear seals to exposed concrete aggregates.
  • Completed in 5 days