image
image
image
image
image
image
image

Project: FOOD MANUFACTURING FACILITY

locations: Stoke

overall size of the project: 300

specification: Polyurethane Screed

    • Prepare substrate via vacuum-enclosed diamond grinding to remove all surface contamination and leave a smooth mechanical finish.
    • Apply Epoxy Primer coat and blind with quartz aggregate
    • Apply 9mm Polyurethane screed in chosen Ral colour.
    • Apply Coved skirting to perimeter areas and bring through expansion joints.
    • Project completed in 3 days
image
image
image
image
image
image
image

request a quote for your project