Project: CHOCOLATE-BASED FOOD MANUFACTURING PLANT
locations: Preston north west uk
overall size of the project: approx. 76M2
system: flexible seamless polyurethane system to the mezzanine deck
- Food processing plant.
- Degreased and mechanically sand to prepare the substrate.
- Cover all joints with fibreglass incorporated into the epoxy primer and allowed to cure.
- Apply epoxy primer to all decks and allow to cure.
- Apply 3-4mm seamless flexible polyurethane screed and allow to cure.
- 1st matt seal.
- 2nd matt seal.
- Completed in 10 days.