Project: BOOTS MANUFACTURING

locations: Nottingham UK

overall size of the project: approx. 44 linear meters

system: smooth transition joint repairs

  • Packing and dispatch
  • Diamond cut on either side with vacuum attached.
  • Breakout to desired depth.
  • Bottom out with fast-curing grout up to template level.
  • Once cured, fixed the sr joint and fill it with epoxy and allow it to cure.
  • Once cured, to re-grind all repairs until equally smooth with all adjacent flooring.
  • Apply clear seals to all over grinds and allow to cure.
  • Completed in 3 days