Project: A.D Harvey Production Expansion

Location:  Norwich

Project Size: Approx  400sqm2

Project Specification: Polyurethane screed

  • Remove all existing failed epoxy coating and prepare substrate via vacuum-enclosed diamond grinding
  • Cut all perimeter anchor points and transitions
  • Apply DPM primer and Blind with quartz aggregates
  • Apply 9mm polyurethane screed in chosen Ral
  • Apply Polyurethane wall render to all 0.5 metre-high concrete kerbs
  • Apply polyurethane jointing compound to all joints and transitions
  • The project was completed in 5 days