Project: A.D Harvey Production Expansion
Location: Norwich
Project Size: Approx 400sqm2
Project Specification: Polyurethane screed
- Remove all existing failed epoxy coating and prepare substrate via vacuum-enclosed diamond grinding
- Cut all perimeter anchor points and transitions
- Apply DPM primer and Blind with quartz aggregates
- Apply 9mm polyurethane screed in chosen Ral
- Apply Polyurethane wall render to all 0.5 metre-high concrete kerbs
- Apply polyurethane jointing compound to all joints and transitions
- The project was completed in 5 days