Project: Unoccupied industrial unit
locations: Birmingham
overall size of the project: approx. 450m2
system: pump polymer regulating screed
- Dilapidation works
- Prepared by captive blasting and diamond grinding to edge works.
- To prime with dpm epoxy primer and fully blind with quartz.
- Apply pump polymer regulating screed at a nominal 7mm.
- Apply 1stwater-based epoxy seal and allow to cure.
- Apply 2ndepoxy seal
- Completed in 7 days .