Project: Weetabix Ltd Engineering Floor Upgrades
Location: Northampton
Project Size: Approx 120sqm2
Project Specification: Polyurethane screed
- Remove all existing failed epoxy coating and prepare substrate via vacuum-enclosed diamond grinding
- Cut all perimeter anchor points and transitions
- Apply DPM primer and blind with quartz aggregates
- Apply 9mm polyurethane screed in chosen Ral
- Apply polyurethane jointing compound to all joints and transitions
- The project was completed in 2 days