Completing Clear Epoxy Seal System With Epoxy DPM Primer & Self-Smoothing Screed For Manufacturing In 10 Days

locations: East midlands UK

overall size of the project: approx. 65M2

system: self-smoothing epoxy screed and clear epoxy seal system

  • Manufacturing shop floor
  • Prepared by captive shot blasting and 3 phased planetary grinders.
  • Apply 1st epoxy dpm primer and allow to cure.
  • Fill all minor imperfections or holes and apply 2nd epoxy primer.
  • Apply 2-3mm epoxy self-smoothing screed and allow to cure.
  • To re-diamond cut all joints and apply the jointing compound.
  • Completed in 10 days